Member State report / Art18 / 2018 / D5 / Denmark / NE Atlantic: Greater North Sea

Report type Member State report to Commission
MSFD Article Art. 18 Interim report on programme of measures
Report due 2018-10-15
GES Descriptor D5 Eutrophication
Member State Denmark
Region/subregion NE Atlantic: Greater North Sea
Reported by Danish Environmental Protection Agency
Report date 2019-03-28
Report access msfd-ART18_Final_28032019.xml
Marine reporting units
Features
Measure code
ANSDK-M007-N
ANSDK-M008-N
ANSDK-M033-EX
ANSDK-M034-EX
BALDK-M007-N
BALDK-M008-N
BALDK-M033-EX
BALDK-M034-EX
Measure name
Preparation of administrative processes for nutrient discharges from aquaculture in open coastal waters in Denmark
Reduction of nutrients from land - River Basin Management Plans 2015-2021
Reduction of nutrients from land - River Basin Management Plans 2009-2015
IMO Resolution MEPC.200(62)
Preparation of administrative processes for nutrient discharges from aquaculture in open coastal waters in Denmark
Reduction of nutrients from land - River Basin Management Plans 2015-2021
Reduction of nutrients from land - River Basin Management Plans 2009-2015
IMO Resolution MEPC.200(62)
Measure category (type)
2a
2a
1b (related to WFD)
1a
2a
2a
1b (related to WFD)
1a
Progress in implementation
Implementation started
Implementation started
Implementation started
Implementation started
Measure withdrawn
No
No
No
No
Reason for withdrawal
Year of implementation (Temporal coverage - timeline for implementation)
2019
2021
2019
2021
Delay
1
0
1
0
Reasons for delay
Mechanism for implementation - national
Mechanism for implementation - national
Other obstacles (Obstacles to implementation)
No
Yes
No
Yes
Type of obstacle
Mechanism for implementation - national
Mechanism for implementation - national
Further information on obstacle (Description)
Many projects involve many stakeholders hence a complicated process and complicated legal procedure. Also in some places technical barriers.
Many projects involve many stakeholders hence a complicated process and complicated legal procedure. Also in some places technical barriers.
Brief description of progress (measurement of effectiveness of measure)
Mid term status for PoM in 2018 shows slow progress in voluntary measures (wetlands, miniwetlands, set a side farmland afforestation). Many projects are in progress as feasibility studies. Effort is focused to obtain the full implementation of measures in 2021. A substantial uptake in the end of period is expected.
Mid term status for PoM in 2018 shows slow progress in voluntary measures (wetlands, miniwetlands, set a side farmland afforestation). Many projects are in progress as feasibility studies. Effort is focused to obtain the full implementation of measures in 2021. A substantial uptake in the end of period is expected.