Member State report / Art18 / 2018 / D2 / Spain / NE Atlantic: Bay of Biscay & Iberian Coast
| Report type | Member State report to Commission |
| MSFD Article | Art. 18 Interim report on programme of measures |
| Report due | 2018-10-15 |
| GES Descriptor | D2 Non-indigenous species |
| Member State | Spain |
| Region/subregion | NE Atlantic: Bay of Biscay & Iberian Coast |
| Reported by | Subdirección General para la Protección del Mar. D.G. Sostenibilidad de la Costa y del Mar. Ministerio para la Transición Ecológica. |
| Report date | 2018-12-21 |
| Report access | msfd-ART18_1.xml |
| Marine reporting units | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Features | |||||||||||
| Measure code | EAI1 |
EAI3 |
EAl2 |
H1 |
H10 |
H13 |
H14 |
H2 |
H4 |
H5 |
H6 |
| Measure name | Improving knowledge on invasive species and related issues |
Mobile application for alert and early detection of alien and invasive species in National Parks |
Alert systems, early detection and rapid eradication of invasive alien species |
Regulation of criteria for compatibility with strategies in accordance with Article 3(3) of Law 41/2010 |
Training programmes designed for fishermen, onboard observers, and staff monitoring stranded animals on coasts, and training for administrative managers |
Encouraging innovative projects to improve the sustainability of aquaculture facilities |
Promoting entrepreneurship: prevention (business innovation) and management (support for the creation of new companies) |
Development of a strategy for visibility and dissemination of the Marine Strategies |
Programme for dissemination at schools
|
ACTIONMED Project: Action Plans for Integrated Regional Monitoring Programmes, Coordinated Programmes of Measures and Addressing Data and Knowledge Gaps in the Mediterranean Sea |
Integrated Territorial Investment (ITI) financial tool for the ‘Mar Menor’ |
| Measure category (type) | 2b |
2b |
2a |
2a |
2b |
2a |
2a |
2b |
2b |
2b |
2b |
| Progress in implementation | Implementation started |
Implementation started |
Implementation started |
Implementation started |
Implementation started |
Implementation started |
Implementation started |
Measure implemented |
Measure implemented |
Measure implemented |
Measure implemented |
| Measure withdrawn | No |
No |
No |
No |
No |
No |
No |
No |
No |
No |
No |
| Reason for withdrawal | |||||||||||
| Year of implementation (Temporal coverage - timeline for implementation) | 2018 |
2019 |
2019 |
2019 |
2019 |
2018 |
2019 |
2018 |
2018 |
2017 |
2016 |
| Delay | 2 |
3 |
3 |
2 |
0 |
2 |
0 |
0 |
2 |
0 |
0 |
| Reasons for delay | Mechanism for implementation - national |
Technical implementation |
Cost-effectiveness |
Acceptance |
Technical implementation |
Technical implementation |
|||||
| Other obstacles (Obstacles to implementation) | Yes |
No |
No |
No |
No |
No |
No |
No |
No |
No |
No |
| Type of obstacle | Financing |
||||||||||
| Further information on obstacle (Description) | La implementación de la medida comenzó en 2016, tal y como estaba previsto en el PoM. |
La implementación de la medida comenzó en 2017, dos años después de la fecha prevista en el PoM. |
|||||||||
| Brief description of progress (measurement of effectiveness of measure) | El sistema ya ha sido desarrollado. Solo falta la inclusión de los cuatro parques nacionales canarios para su puesta en marcha completa. |
La implementación de la medida comenzó en 2016, tal y como estaba previsto en el PoM. |
La implementación de la medida comenzó en 2017, tal y como estaba previsto en el PoM. |
La implementación de la medida comenzó en 2015 como estaba previsto en el PoM |
El proyecto se desarrolló de 2015 a 2017, tal y como estaba previsto en el PoM. |