Member State report / Art18 / 2018 / D2 / Finland / Baltic Sea
| Report type | Member State report to Commission |
| MSFD Article | Art. 18 Interim report on programme of measures |
| Report due | 2018-10-15 |
| GES Descriptor | D2 Non-indigenous species |
| Member State | Finland |
| Region/subregion | Baltic Sea |
| Reported by | Finnish Environment Institute (SYKE) |
| Report date | 2018-12-21 |
| Report access | BALFI-ART18_21DEC2018.xml |
| Marine reporting units | ||||||||
|---|---|---|---|---|---|---|---|---|
| Features | ||||||||
| Measure code | BALFI-M026-HABIT |
BALFI-X001-NIS |
BALFI-X002-NIS |
BALFI-X003-NIS |
BALFI-X004-NIS |
BALFI-X004-SHIP |
BALFI-X005-NIS |
BALFI-X005-SHIP |
| Measure name | HABIT2 - Action plans for endangered species and habitats |
Saving Nature for People. National action plan for the conservation and sustainable use of biodiversity in Finland 2013–2020 (Government Resolution 20 December 2012) |
Challenges and Policies of the Baltic Sea Region, Government report on action against harmful Non-Indigenous Species (2009) |
National strategy for Non-Indigenous Species (Government resolution 15 March 2012) |
Measures that relate to the EU Regulation (1143/2014/EU) on the prevention and management of the introduction and spread of invasive alien species |
Government Decree (2/2000) on the Implementation of the Convention on the Protection of the Marine Environment of the Baltic Sea |
Measures that relate to the government proposal for a law on the management of the risks caused by invasive alien species, which will implement the EU Regulation (1143/2014) |
Act on the Exclusive Economic Zone of Finland (1058/2004) |
| Measure category (type) | 2a |
1a |
1a |
1a |
1a |
1a |
1a |
1a |
| Progress in implementation | Implementation started |
|||||||
| Measure withdrawn | No |
|||||||
| Reason for withdrawal | ||||||||
| Year of implementation (Temporal coverage - timeline for implementation) | 2020 |
|||||||
| Delay | 0 |
|||||||
| Reasons for delay | ||||||||
| Other obstacles (Obstacles to implementation) | No |
|||||||
| Type of obstacle | ||||||||
| Further information on obstacle (Description) | ||||||||
| Brief description of progress (measurement of effectiveness of measure) | The strategy has been adopted and it is ongoing and being implemented by ongoing measures. |
The strategy has been adopted and it is ongoing and being implemented by ongoing measures. |